Act 250 Roundup 2003
During 2003, the Vermont Environmental Board received 654 permit applications
for Act 250,Vermont’s land-use law. Estimated construction costs for the projects total $337 million. Here’s a list of Act 250 applications throughout Vermont with costs higher than $250,000. Projects are listed according to district and construction costs. Source:Vermont Environmental Board/Denise Wheeler
| Applicant | Location | Date | Cost | Project |
| District 1: Rutland County, 7 permits, $15,880,685 | ||||
| Castleton State College | Castleton | 11/12/03 | $6,280,500 | 3-story, 152-bed residence hall; adjoining 2-story fitness center, new parking lot and landscaping |
| S.T. Griswold and Co. Inc. | Rutland City | 1/27/03 | $5,113,000 | Phased construction of 61-lot affordable housing |
| The Lodges at Bear Mountain LLC | Killington | 7/14/03 | $1,989,435 | One building containing 12 residential condominium units; conditional approval for second |
| General Electric Co. | Rutland Town | 11/10/03 | $909,000 | Construction and use of enhanced security facilities Including a guard house, fencing, gates, etc. |
| Glenbrook Manufacturing Corp. | Castleton | 7/22/03 | $683,000 | 80' x 300' building addition; 30' x 76' addition between existing buildings; 8' x 8' building addition |
| Kalow Technologies Inc. | Clarendon | 9/22/03 | $463,750 | Construct 14,400-sf addition to existing facility |
| Brandon Area Rescue Squad Inc. | Brandon | 7/28/03 | $442,000 | 60' x 80' , 1 1/2 story structure w/ full basement; 3 ambulance bays |
| District 2: Windham and Southern Windsor Counties, 19 permits, $24,925,022 | ||||
| Homestead Design Inc. | Hartford | 6/30/03 | $5,628,000 | Construct 16 3-story buildings. 10 will contain three 3-bedroom townhomes, 5 will contain two 3-bedroom |
| Moping Owl Corp. | Hartford | 4/11/03 | $3,000,000 | Construct a 6-building office condominium campus totaling 36,000 sf |
| Bellows Falls Village | Rockingham | 9/11/03 | $2,125,740 | Water system and storage improvement |
| Delta Industries | Brattleboro | 9/15/03 | $1,870,400 | Construct a 28,400-sf manufacturing facility on lot 4 to make optic filters |
| Okemo Mountain Inc. | Ludlow | 6/5/03 | $1,800,000 | Expand existing snowmaking pond and dam |
| Kingswood of Vermont Inc. | Dover | 1/21/03 | $1,645,200 | Construct 9 buildings with 18 duplex units |
| Stratton Mountain School | Stratton | 5/16/03 | $1,500,000 | Constructing 70' x 110' addition onto existing field house |
| Woodstock Resort Corp. | Woodstock | 1/13/03 | $1,311,799 | Demolish Paul house and reconstruct |
| Okemo LLC | Ludlow | 1/31/03 | $1,033,500 | Upgrade lift B1 from fixed grip quad chair to detachable quad chair lift |
| Vermont Academy | Rockingham | 4/17/03 | $800,000 | Construct 2,500 sf of new locker room area, 1,000 sf of new entrance lobby renovate existing locker |
| Twin Farms LLC | Barnard | 9/22/03 | $665,000 | Construct Cottage X in a new location |
| Twin Farms LLC | Barnard | 11/5/03 | $650,000 | Exchange the Hamilton lot for permitted Site Y for use as a cottage |
| Stratton Corp. | Stratton | 7/22/03 | $623,623 | Construct remainder of ski trails based on master plan, modifying for less impact on wetlands and wildlife |
| Russell, Jr. Dimmick/R.S.L. LLC. | Royalton | 3/6/03 | $560,000 | Construct a 120' x 80' building for sales and service |
| Green Mountain Insulation of Vt. | Hartford | 4/29/03 | $470,000 | Construct two 5,000-sf warehouses with office space |
| North Hartland Dry Kilns Inc. | Hartland | 2/18/03 | $400,000 | Construct 100' x 200' steel building for lumber storage |
| Cobur Inc. | Brattleboro | 9/24/03 | $341,760 | Demolish existing building to construct a 2,800-sf 4-bay car wash |
| Magic Mountain Management LLC | Londonderry | 7/28/03 | $250,000 | Improve existing snow tubing park |
| Auto Mall Inc. | Brattleboro | 4/2/03 | $250,000 | 3,600 sf addition to existing 7,500-sf facility |
| District 3: Orange & Northern Windsor Counties, 2 permits, $2,301,715 | ||||
| R.E.M. Bradford Development Co. LLC | Bradford | 4/21/03 | $1,515,000 | Construction of four new commercial buildings |
| Randolph Area Community | Randolph | 2/3/03 | $786,715 | Construct two buildings, containing a total of eight dwelling units |
| Development Corp. | w/related infrastructure on a 2.4-acre lot | |||
| District 4: Chittenden County, 29 permits, $52,819,419 | ||||
| St. Michael’s College | Colchester | 4/18/03 | $12,600,000 | Construction of two 3-story residence halls |
| Sterling Construction | Shelburne | 4/1/03 | $5,795,500 | Planned residential development |
| City of S. Burlington | S. Burlington | 7/17/03 | $5,600,000 | Widening of Kennedy Drive from Dorset Street to Williston Road to four lanes |
| John Larkin | S. Burlington | 7/23/03 | $5,269,670 | Construction of 6-story, 113-room elderly housing complex on Lot #6 of Bartlett subdivision |
| Pine Ridge School | Williston | 5/23/03 | $3,115,100 | Two dormitory buildings |
| Homestead Design | Essex Jct. | 3/21/03 | $2,052,485 | 30 units of affordable apartments |
| Husky Injection Molding Systems Inc. | Milton | 3/14/03 | $1,940,400 | Construction of 17,650-sf manufacturing addition to hot runner building |
| Lodging North Inc. | S. Burlington | 7/14/03 | $1,900,000 | Addition of 33 suites to existing hotel |
| Farwater Ltd. | S. Burlington | 1/31/03 | $1,614,000 | One additional 44 unit building |
| Tucker And Michelle Holland | Shelburne | 7/14/03 | $1,400,000 | Subdivide 32-acre parcel of land into three building lots |
| Shelburne Bay Senior Living Community | Shelburne | 11/12/03 | $1,330,000 | Addition of 48 senior housing units w/parking |
| Whitcomb Woods Housing Limited | Essex Jct. | 7/14/03 | $1,054,200 | Construction of 20 1-bedroom elderly housing units |
| Partnership | ||||
| Haydenberry Holdings LLC | Milton | 5/6/03 | $939,440 | Phase I: construct 3 buildings |
| Steve Reynolds | Milton | 4/11/03 | $820,500 | 36-lot subdivision |
| Chittenden South Supervisory Union | Hinesburg | 8/4/03 | $700,000 | Construction of two 18,000-sf athletic fields, parking, grading of second parking area |
| GP Burlington North LLC | Burlington | 8/8/03 | $675,000 | Construction of 10,444-sf footprint addition w/4,436-sf mezzanine to building 21 |
| Bill Dunn/Hillside East Corp. | Williston | 4/29/03 | $649,802 | Construct office building with 73 parking spaces/lot 9 |
| Marv Greenberg/Animal Hospital of Vt. | Hinesburg | 6/13/03 | $625,000 | Construction of new one-story 4,200-sf animal hospital on lot #7 |
| Bay’s End LLC | Shelburne | 9/10/03 | $620,500 | Creation of 5-lot subdivision w/boundary line adjustment w/Perrigo property |
| University of Vermont | Burlington | 9/16/03 | $573,000 | Renovation of carriage house to 2,870-sf admissions visitor center |
| White Bear LLC | Milton | 6/2/03 | $532,800 | 7-unit residential townhouse building |
| Joe Jordan | Essex | 4/10/03 | $526,400 | 4-lot residential subdivision adjacent to meadow’s edge |
| Joe Jordan | Essex | 5/28/03 | $479,000 | Creation of four residential lots |
| University Wholesalers dba Round Realty | Colchester | 6/13/03 | $381,622 | Construction of 5,479-sf addition to existing building |
| University of Vermont | Essex | 6/19/03 | $375,300 | Demolition and reconstruction of existing Fort Ethan Allen Building #1003/4-unit building |
| Essex Mini Storage | Essex | 1/23/03 | $340,000 | Construction of 20,000-sf commercial record storage |
| Engelberth Properties Inc. | Colchester | 8/14/03 | $332,450 | Construction of 112 space parking lot on lot A-12 to accommodate needs for lots 22 and 24 |
| Spillane’s Towing and Recovery | S. Burlington | 8/8/03 | $327,250 | Construction of 8,750-sf commercial building for office, garage/warehouse/lot #35 |
| Kenneth Smith | S. Burlington | 10/24/03 | $250,000 | Construction of 7,200-sf commercial building on Lot #24 of Ethan Allen Industrial Park |
| District 5: Washington & Lamoille Counties,15 permits, $21,355,145 | ||||
| Patrick Malone | Montpelier | 9/18/03 | $4,750,000 | Two industrial buildings: a refrigerated warehouse and a storage building for dry goods |
| Stowe Family Housing | Stowe | 5/2/03 | $4,520,000 | 42 residential units in five 2-story buildings |
| Smugglers’ Notch Management Co. Ltd. | Cambridge | 2/3/03 | $3,916,095 | 118 residential units |
| Pilgrim Partnership | Waterbury | 9/19/03 | $3,248,000 | 52,000-sf warehouse and distribution facility for Green Mountain Coffee Roasters |
| Jewish Community of Greater Stowe | Stowe | 6/27/03 | $946,800 | 6,000-sf community center and relocation of Stowe bike path |
| Fred J. Connor/The Connor Group | Berlin | 2/11/03 | $800,000 | Phase I of redeveloping building |
| State of Vermont/Dept. of Buildings | Waterbury | 2/5/03 | $465,000 | 119 additional parking spaces at four locations |
| Lamoille County Planning Commission | Stowe | 1/8/03 | $450,000 | Southern gateway to Smugglers’ Notch Scenic Highway corridor |
| John W. Anderson | East Montpelier | 3/14/03 | $393,750 | 15,750-sf building |
| Golden Eagle Resort | Stowe | 2/10/03 | $390,000 | Addition to existing restaurant building |
| Randal Lague/Superior Development Ltd. | Berlin | 8/22/03 | $386,000 | 5,000-sf professional office building |
| Stephen Levin/Levin Family Trust | Stowe | 8/20/03 | $302,000 | 3-bedroom cottage and subdivide 3-acre lot for new residence |
| Hillside Realty LLC | Barre Town | 7/8/03 | $271,000 | 70' x 70' building to house granite countertop manufacturing facility |
| RCC Atlantic Inc. | Moretown | 4/17/03 | $263,500 | Install telecommunications panel antenna |
| Dale E. Percy | Stowe | 1/16/03 | $253,000 | 8,000-sf building for indoor storage and warehouse space |
| District 6: Franklin & Grand Isle Counties, 13 permits, $70,497,854 | ||||
| Vermont Agency of Transportation | Alburg | 3/20/03 | $55,000,000 | Construct 3,584' bridge and remove 330' of existing causeway from old bridge |
| Vermont Agency of Transportation | Highgate | 1/28/03 | $5,975,628 | Reconstruction of Town Highway 3 |
| Vermont Agency of Transportation | Berkshire | 3/10/03 | $2,750,000 | Construction of replacement bridge on Vt. Route 118 over Trout River |
| Yandow/Dousevicz Construction Co. | St. Albans Town | 2/18/03 | $2,000,000 | Congregate care facility |
| JLB St. Albans LLC | St. Albans Town | 5/21/03 | $1,125,000 | 3-lot commercial subdivision: bank, fast food restaurant, 11,500-sf building |
| Joe Stuart | Georgia | 6/13/03 | $721,986 | Create a 42-unit prd w/18 single-family homes, 23 townstyle units |
| Grand Isle Enterprises, LLP | Grand Isle | 7/11/03 | $675,000 | Subdivide tract of land into two lots and construct 16-unit multifamily housing project on lot 2 |
| Sunhill Food of Vermont | Swanton | 8/18/03 | $575,000 | 8,000-sf manufacturing addition, 1,000-sf lunchroom addition, 300-sf boiler room addition to existing building |
| James & Janet Harrison | Georgia | 2/10/03 | $480,000 | Construction of concrete batching plant |
| Church of the Rock | St. Albans | 8/13/03 | $400,500 | Construct 3,200-sf addition to existing church and modifications to entrance |
| Ingleside Equity Group | St. Albans | 4/7/03 | $272,740 | Subdivide 9.8 acres into 10 single-family residential lots |
| Town of North Hero | North Hero | 8/8/03 | $265,000 | Construct two 3,000-gallon water storage tanks |
| Bruno & Stephane Fantin | Isle La Motte | 4/3/03 | $257,000 | Construct 8,400-sf warehouse addition to existing warehouse building |
| District 7: Caledonia, Orleans, & Essex Counties, 9 permits, $7,345,959 | ||||
| Jay Peak Inc. | Jay | 4/15/03 | $1,995,000 | Construct #14 and condos #4 and #5 |
| NVDA | Lyndon | 2/10/03 | $1,045,029 | Construct 21,000-sf office facility/warehouse/job training facility |
| City of Newport | Newport | 2/4/03 | $987,530 | Construct 2.0 miles of non-motorized path |
| Northeast Kingdom Learning Services Inc. | Barton | 6/2/03 | $665,000 | Construct 10,800-sf educational building |
| Corner Medical Associates | Lyndon | 9/11/03 | $653,000 | Construct 900-sf addition to existing former system sales building |
| Jay Peak Inc. | Jay | 3/17/03 | $590,000 | Construct townhouse #8 (second 4-unit building) in Village II |
| St. Johnsbury Automobile Co. LLC | St. Johnsbury | 7/9/03 | $575,000 | Demolish existing building and construct a new 14,000-sf sales/repair facility |
| Cumberland Farms Inc. | Newport | 6/11/03 | $485,400 | Demolish existing store and construct new convenience store, gas pumps, etc. |
| Northern New England Assembly of God | Hardwick | 2/3/03 | $350,000 | Construct 5,766-sf church and related parking, landscaping, etc. |
| District 8: Bennington County, 7 permits, $8,371,015 | ||||
| Bennington Acres | Bennington | 2/20/03 | $3,200,000 | Construct new 80-room Hampton Inn on 2.52 acres |
| John & Jim Hand/Hand Motors | Manchester | 1/15/03 | $1,766,220 | Expansion of car dealership; construction of 20,851-sf parts and service bldg. |
| RAHC | Manchester | 5/19/03 | $1,113,886 | Construct 15 units affordable housing in three buildings; parking for 32 cars |
| Wendy’s of New York Inc. | Bennington | 8/1/03 | $862,500 | Construct 94-seat, 3,000-sf Wendy’s restaurant |
| American Museum of Fly Fishing | Manchester | 10/24/03 | $595,586 | Demolish, renovate and restore portions of main house to be used as museum gallery |
| Oly Equinox Holdings LLC | Manchester | 6/4/03 | $482,823 | Revisions to parking lot at Equinox Hotel |
| District 9: Addison County, 2 permits, $2,375,000 | ||||
| Town of Manchester | Manchester | 11/24/03 | $350,000 | Construct multipurpose athletic field, 360' x 225' w/ 4 70' high light fixtures |
| Town of Middlebury | Middlebury | 7/2/03 | $2,100,000 | Construct 7,621-sf building |
| Delineation Corp. | Middlebury | 11/13/03 | $275,000 | Construction 30,000-sf industrial warehouse building |