Act 250 Rundown
This is a list of approved Act 250 applications for commercial projects in 2011 throughout Vermont with costs higher than $250,000. Projects are listed according to district and construction costs. Source: Louis Borie, chief coordinator, Natural Resources Board
| Applicant/Organization | Location | Construction Cost | Project Description | County |
| District 1: Rutland County, 5 Permits, $16,748,420 | ||||
| Killington/Pico Ski Resort Partners LLC | Killington | $10174,500 | Replace Peak Lodge/gondola terminal w/three-story, 25,000 sf lodge; replace wastewater system | Rutland |
| State of Vermont, Maintenance & Aviation | Clarendon | $3,800,000 | Realign Airport Road; widen and extend runway 19 safety area | Rutland |
| Vermont Electric Power | Rutland Town | $1,940,920 | New 11,952 sf warehouse; convert existing warehouse into office building | Rutland |
| Vangaurd-Fine LLC | Rutland | $583,000 | 4,000 sf restaurant/bakery | Rutland |
| Central Vermont Public Service Corp. | Wells | $250,000 | 9,934 feet of new utility line corridor on East Wells Road | Rutland |
| District 2: Windham and Southern Windsor Counties, 12 Permits, $12,388,830 | ||||
| Friends of Algiers Village Inc.; Windham & Windsor Housing Trust; Town of Guilford | Guilford | $2,684,000 | 15-unit apartment building and duplex, parking, access; remove old structures | Windham |
| Vermont Law School | Royalton | $2,466,500 | Convert 188-190 Chelsea St. to clinician and bookstore use | Windsor |
| Ceresosimo Lumber Co. Inc. | Brattleboro | $1,600,000 | Demolish dry kiln; build 9,400 sf dry kiln | Windham |
| IDDS LLC | Guilford | $1,130,000 | Merge three lots and re-subdivide into two lots | Windham |
| Vermont Law School | Royalton | $900,000 | Demolish Fay House, sand/salt storage; build fitness center | Windsor |
| Snow Country Snowmobile Tours | Cavendish | $807,770 | Planned-unit development: three buildings, each w/two 4-bedroom, single-family units | Windsor |
| Vermont Farmstead Cheese Corp.; Springfield Reg. Development Corp.; Great Bear Realty Corp. | Windsor | $650,000 | 11,250 sf agricultural cooperative building | Windsor |
| Family Dollar; Sam St. John Trust | Wilmington | $608,615 | Demolish True Value building; construct 9,768 sf building | Windham |
| Mount Snow Ltd. | Dover | $477,945 | Storage building for chairlift chairs; bury fiber-optic line | Windham |
| Mount Snow Ltd. | Dover | $400,000 | Widen and upgrade Long John Trail | Windham |
| Hermitage Inn Real Estate Holding Co. | Dover | $375,000 | Build trail connecting Haystack Ski area to Hermitage Inn | Windham |
| 42 Village Green LLC; Village Green LLC | Cavendish | $289,000 | Renovate structure for restaurant w/indoor recreation areas | Windsor |
| District 3: Orange and Northern Windsor Counties, 5 Permits, $4,164,948 | ||||
| Hartford Area Vocational Technical Center; Town of Hartford; Brookemeade Circle | Hartford | $1,870,640 | 10-lot subdivision of nine single-family homes; extend Brookmeade Circle Road | Windsor 3 |
| Charward LLC | Hartford | $752,000 | Add three climate-controlled self-storage buildings | Windsor 3 |
| Zaremba Land Development LLC | Williamstown | $612,308 | Build and operate Dollar General store | Orange |
| FD Bradford VT LLC; Centerplan Development Co. LLC | Bradford | $480,000 | 8,000 sf retail store and 32-car parking lot | Orange |
| Telephone Operating Co. of Vt.; Central Vermont Public Service | Woodstock | $450,000 | Relocate and rebuild 8,872 feet of electrical and telephone lines | Windsor 3 |
| District 4: Chittenden County, 42 Permits, $184,085,938 | ||||
| St. Michael’s College | Colchester | $23,086,000 | Build student center; connect to residence for 105 students | Chittenden |
| Champlain College | Burlington | $22,992,500 | Three residential halls, green space, amphitheater, promenade, and infrastructure | Chittenden |
| City of Burlington; Vermont Agency of Transportation | Burlington | $20,000,000 | Complete the Champlain Parkway | Chittenden |
| Miller Realty Group LLP; Green Mountain Coffee Roasters Inc. | Essex | $18,000,000 | 235,375 sf addition w/loading, parking, stormwater | Chittenden |
| VTrans | Charlotte | $12,100,000 | Rebuild US 7 and pedestrian bike path | Chittenden |
| Champlain College | Burlington | $11,199,120 | Add 41,900 sf to Hauke Center and Alumni Hall | Chittenden |
| F&M Development Co. LLC | S. Burlington | $9,880,000 | Demolish building, build two buildings to house 111 units | Chittenden |
| Heritage Automotive Group Inc. | S. Burlington | $7,039,136 | Replace building w/35,032 sf auto service building plus 600 sf addition to sales building | Chittenden |
| The Miller Group | Milton | $7,000,000 | 138,000 sf distribution warehouse and loading docks | Chittenden |
| Acabay Inc. | Colchester | $6,000,000 | 75,000 sf general office building w/parking | Chittenden |
| Pizzagalli Properties LLC | S. Burlington | $4,300,000 | Two-story, 50,000 sf office building | Chittenden |
| Taft Corners Associates | Williston | $4,075,900 | Two mixed-use commercial buildings, 29,140 sf | Chittenden |
| DEW, Rte. 2A Investments | Colchester | $3,388,000 | Planned-unit development: two 8-unit office/warehouse buildings, seven mini-storage buildings; 9.95 acres | Chittenden |
| Southerly Side of US Route 7 LLC | Milton | $3,261,000 | Final phase: 52 residential units | Chittenden |
| Chittenden East Supervisory Union; Mount Mansfield Union High School; Town of Richmond | Richmond | $3,097,939 | Renovate parking lot to improve vehicle ciculation; reconfigure storm drain system | Chittenden |
| Wedgewood Development Corp. | Colchester | $2,842,000 | 20-lot planned-unit development: 19 single-family homes; one common-area parcel | Chittenden |
| G.B. New England 2 LLC | Williston | $2,780,000 | Two-story, 19,840 sf pharmacy; demolish existing structure | Chittenden |
| City of South Burlington | S. Burlington | $2,450,000 | Widen US 2 near the Sheraton Hotel | Chittenden |
| Town of Milton | Milton | $2,425,000 | Build sewer mains in the town core; new pump station | Chittenden |
| NPC Processing Inc. | Shelburne | $2,100,000 | 24,375 sf two-story food processing facility | Chittenden |
| Chittenden Solid Waste District | Williston | $1,767,000 | Increase compost pad by 4,500 sf; relocate bagging building; insulate and heat | Chittenden |
| TruexCullins Architecture | S. Burlington | $1,504,000 | New entrance; relocate snack bar and bathrooms | Chittenden |
| Regal Gymnastics | Essex | $1,200,000 | 17,500 sf gymnastics center; 74 parking spaces | Chittenden |
| Pomerleau Real Estate; 10 Executive Drive LLC | Shelburne | $1,192,500 | 11,500 sf drugstore | Chittenden |
| CD Cairns Irrevocable Trusts | Hinesburg | $1,125,000 | Rebuild and expand Ballard Store into Jiffy Mart w/gas sales | Chittenden |
| Vermont Federal Credit Union | Milton | $951,500 | 3,100 sf branch; merge two lots of previous subdivision | Chittenden |
| Village Associates | Williston | $932,500 | Modify approved project: changes to buildings Z and H | Chittenden |
| Woolen Mill Associates | Winooski | $765,000 | Five 1-bedroom apartments and management office | Chittenden |
| Aaron Vincelette | Williston | $760,659 | Partial findings for a 10,950 sf car wash | Chittenden |
| Vermont Technical College | Williston | $602,500 | Change use of 3-story office/classroom to a 25-bed dorm | Chittenden |
| Toys“R”Us | Williston | $582,270 | Master sign plan; modify exterior façade; new building | Chittenden |
| Homestead Design Inc. | Essex | $575,000 | 3,000 sf bank building; parking; temporary road | Chittenden |
| Champlain Housing Trust Inc. | Burlington | $550,000 | Convert 4-apartment building into 15-bedroom, 1-kitchen group home | Chittenden |
| Town of Shelburne | Shelburne | $536,612 | Bike/pedestrian path along Webster Road | Chittenden |
| Champlain Valley Exposition Inc. | Essex Junction | $500,000 | Event-staging area | Chittenden |
| Shelburne Green LLC | Shelburne | $492,000 | Phase II: Convert 43,000 sf light manufacturing use into office use; parking lot | Chittenden |
| Meadowridge Community Association | Williston | $425,000 | Change disposal system and connect to municipal sewer | Chittenden |
| Hergenrother Construction | Colchester | $407,800 | Remove single-family home; build two duplex units | Chittenden |
| City of South Burlington | S. Burlington | $350,000 | Stormwater treatment pond | Chittenden |
| Brad Morse | Essex | $325,000 | Renovate unpermitted 9,625 sf cold-storage warehouse | Chittenden |
| The Miller Group | Essex | $275,000 | 5,400 sf commercial building; demolish building | Chittenden |
| McDonald’s Corp. | Colchester | $250,000 | Interior and exterior renovations; 23 sf addition for relocated drive-thru window; ADA parking | Chittenden |
| District 5: Washington and Lamoille Counties, 5 Permits, $27,878,591 | ||||
| Summit Ventures NE LLC | Warren | $6,673,488 |
Revisions; continued redevelopment: Lincoln Peak base area |
Washington |
| Mt. Mansfield Co. Inc. | Stowe | $6,450,000 | 5,900 sf detachable quad lift to replace Forerunner | Lamoille |
| Berlin Automotive T1 LLC | Berlin | $2,922,768 | Demolish car dealership; build replacement | Washington |
| Mayo Health Care Inc. | Northfield | $2,438,440 | Building addition and seven smaller bump-out additions | Washington |
| Moretown Landfill Inc. | Moretown | $1,822,000 | Expand soil/stone extraction area; build access road; change stormwater collection system | Washington |
| Vermont Butter & Cheese | Barre Town | $1,750,000 | Add production/processing space and truck bay for raw milk delivery | Washington |
| True North Wilderness Programs LLC | Fayston | $1,295,000 | Support center; sugar house and storage garage for ATVs and snowmachines; 12 camp sites | Washington |
| Norwich University | Northfield | $877,835 |
Build and operate outdoor recreation center |
Washington |
| The Health Center | Plainfield | $832,000 |
4,500 sf accessory building for counseling facility |
Washington |
| AutoZone Northeast Inc. | Berlin | $824,000 | Auto parts store, Overlook Plaza | Washington |
| Smugglers’ Notch Management Co. Ltd. | Cambridge | $687,160 | Replace stressed membrane structure; use as interim administration facility | Lamoille |
| Vermont Slate and Copper Services Inc. | Morristown | $687,000 | 13,500 sf addition to manufacturing facility | Lamoille |
| Union Bank | Jeffersonville | $618,900 | Build and operate bank | Lamoille |
| District 6: Franklin and Grand Isle Counties, 10 Permits, $11,372,615 | ||||
| Peerless Clothing International Inc. | St. Albans Town | $4,279,400 | 72,000 sf addition to Building D for storage and distribution | Franklin |
| Hawk’s Nest South, LLP | St. Albans Town | $2,245,000 | 49-unit, 3-story senior housing; underground parking | Franklin |
| City of St. Albans | St. Albans | $800,000 | Demolish Fonda Building; abate hazardous materials; environmental mediation | Franklin |
| Town of Swanton | Swanton | $713,300 | Subdivide 23.8 acres into five industrial lots; new road, stormwater system; utilities | Franklin |
| Remy Vallee | St. Albans Town | $679,000 | Mixed-use building: dental office and two residential units | Franklin |
| Vermont Agency of Transportation | Highgate | $675,000 | Snow-removal equipment storage building and airplane hangar | Franklin |
| Raymond Gadue | Highgate | $672,500 | 12,950 sf addition to commercial building | Franklin |
| Burnett Scrap Metals LLC | Georgia | $551,000 |
10,400 sf recycle center on Lot 4, Morse ndustrial Park |
Franklin |
| Bellows Free Academy Union School District | St. Albans Town | $395,415 | One-story addition for locker room | Franklin |
| McDonald’s Corp. | St. Albans Town | $362,000 | Demolish building; erect 4,500 sf restaurant w/drive-thru | Franklin |
| District 7: Caledonia, Orleans, and Essex Counties, 11 Permits, $35,014,326 | ||||
| Jay Peak Inc. | Jay | $11725,052 | Phase 2, Golf & Mountain Suites | Orleans |
| American Better Community Developers | Derby | $5,450,000 | 30,174 sf office building; parking, lighting, landscaping, utility connections | Orleans |
| Jay Peak Inc. | Jay | $4,281,141 | One 5-unit building; one townhouse (South Village 1,2,3) | Orleans |
| Gilman Housing Inc. | Newport City | $3,506,316 | 16 residential units; demolish five buildings | Orleans |
| Jay Peak Inc. | Jay | $3,122,000 | 11 buildings, 34 units, Golf & Mountain Suites | Orleans |
| Burke 2000 LLC | Burke | $2,360,000 | High-speed quad; some trail changes | Caledonia |
| Audrey H. Dunn Revocable Trust | Craftsbury | $1,750,317 | Demolish and rebuild facility | Orleans |
| Vermont Electrical Cooperative Inc. | Hardwick | $1,000,000 | 5,000 sf extended-family household; 5,000 sf multipurpose building | Caledonia |
| Lyndon State College | Lyndon | $909,000 | Rebuild and expand Stonehenge parking lot | Caledonia |
| Jay Peak Inc. | Jay | $585,500 | On-mountain improvements | Orleans |
| State Buildings Division | Newport | $325,000 | 40-space parking area, Northern State Correctional Facility | Orleans |
| District 8: Bennington County, 6 Permits, $5,012,300 | ||||
| REE&C Capital Management Services | Manchester | $2,190,000 | Subdivide 5.2-acre parcel into two lots; erect library building | Bennington |
| Equinox Foundation LLC | Manchester | $1,263,300 | Visitor center, observation deck; resurface parking lot | Bennington |
| NSK Steering System Inc. | Bennington | $459,000 | 30’x140’ addition to shipping department; demolish house; build truck access; lanscaping | Bennington |
| Bromley Mountain Equity Ltd. Partnership | Peru | $400,000 | 36’x54’ base lodge enclosure | Bennington |
| Bromley Mountain Equity Ltd. Partnership | Peru | $350,000 | Regrade Beginners’ Circle; replace two tows w/lift; build 16’x30’ hut | Bennington |
| District 9: Addison County, 4 Permits, $3,033,572 | ||||
| A. Johnson Co. | Middlebury | $1,397,600 | Planned-unit development w/43 single-family homes, six lots undeveloped; road | Addison |
| Addison County Humane Society | Middlebury | $762,972 | 2,800 sf barn for kennels and support function; 1,650 sf 2-story office | Addison |
| Martin and Carol Kulczyk | Ripton | $543,000 | 10 rental cabins | Addison |
| President & Fellows of Middlebury College | Middlebury | $330,000 | Rebuild Khon Athletic Field; install four exterior shields to reduce light spillage | Addison |
This is a list of approved Act 250 applications for commercial projects in 2011 throughout Vermont with costs higher than $250,000. Projects are listed according to district and construction costs.
Source: Louis Borie, chief coordinator, Natural Resources Board